How does a subdivision application work?
The application goes through the Ministry of Public Works (Subdivision and Sanitation Plans department). The steps differ per type of subdivision.
- Small subdivision: intake, quick scan, processing, draft permit and then the permit.
- Large subdivision: intake, quick scan, processing, a declaration of readiness (bereidverklaring), execution of the works and then the permit. Advice on roads, traffic and drainage and a field inspection are part of this.
Always check with the ministry that this overview is still up to date. Source: Subdivision Manual 2022 (Handleiding Verkavelingen), Ministry of Public Works. Last checked: October 2026.
What does Major One do for you?
- We go through with you which documents are needed for your situation.
- We carry out the surveying work and prepare the subdivision plan and the required maps, such as the subdivision map.
- We check your file for completeness before submission, so that you avoid unnecessary delay.
- For the spot height map (hoogtecijferkaart), height surveys are needed.
For large subdivisions, according to the manual of the ministry, the application and design must be prepared by a registered engineering firm. We discuss with you which parts we carry out ourselves and where an engineering firm is needed.
Which documents do you need?
Which documents you need depends on the type of application, the purpose and the number of lots. Submit all documents in triplicate; at least one copy is an original. Plans have a scale of at least 1:1000.
For every application
- Request letter (legalised): the official request for permission for the subdivision.
- Fees (leges): proof of payment of the fees due.
- Mortgage extract (hypothecair uittreksel): information about the mortgage registration of the parcel. It may not be older than 28 days.
- Parent map (moederkaart) with Parcel ID: the map of the original parcel. Does your parcel not have a Parcel ID yet? Read how to apply for a Parcel ID.
- Land allocation decision (grondbeschikking) or deed of transfer: the document showing your right to the land.
- Google Earth photo in colour: with the parcel to be divided clearly marked.
- Subdivision map (verdelingskaart): the proposed division of the parcel.
- Site sketch (situatieschets): with distances to parcel boundaries, existing buildings and any obstacles.
Extra for large subdivisions
Large subdivisions (more than 10 lots) and commercial large subdivisions require additional technical plans: a design report with calculations, a spot height map, a traffic, signage and road marking plan and a utilities plan or utilities map. A road plan and a drainage plan are also required for large family subdivisions.
Overview per type of subdivision
| Document | Family large, up to 10 lots | Family large, more than 10 lots | Family small | Commercial large | Commercial small |
|---|---|---|---|---|---|
| Legalised request letter (verzoekschrift) | Yes | Yes | Yes | Yes | Yes |
| Fees (leges) | Yes | Yes | Yes | Yes | Yes |
| Mortgage extract (hypothecair uittreksel) | Yes | Yes | Yes | Yes | Yes |
| Parent map (moederkaart) with Parcel ID | Yes | Yes | Yes | Yes | Yes |
| Land allocation decision (grondbeschikking) | Yes | Yes | Yes | Yes | Yes |
| Google Earth photo in colour | Yes | Yes | Yes | Yes | Yes |
| Subdivision map (verdelingskaart) | Yes | Yes | Yes | Yes | Yes |
| Site sketch (situatieschets) | Yes | Yes | Yes | Yes | Yes |
| Road plan | Yes | Yes | No | Yes | No |
| Drainage plan | Yes | Yes | No | Yes | No |
| Design report with calculations | No | Yes | No | Yes | No |
| Spot height map (hoogtecijferkaart) | No | Yes | No | Yes | No |
| Traffic, signage and road marking plan | No | Yes | No | Yes | No |
| Utilities plan or utilities map | No | Yes | No | Yes | No |
Check with the ministry that this overview is still up to date. Last checked: October 2026.
Extra documents, depending on your situation
- Authorisation letter or power of attorney: if someone submits on behalf of the entitled party.
- Extract from the Chamber of Commerce and Industry (KKF) or the statutes of the foundation: if a company or foundation is involved.
- Death certificate, certificate of inheritance or family tree: if the parcel is part of an estate or family relationships need to be shown.
- Change of zoning designation: if the designation has to change.
- Notarial declaration of family division: if the parcel is divided among family members.
- Declaration of road transfer: if land for a road is transferred.
Not everyone has to submit everything. We go through with you what is needed in your situation.
Practical requirements
- All documents in triplicate, at least one original, single-sided and in colour.
- Plans at a scale of at least 1:1000.
- After the submission on paper, the ministry also asks for a digital file (shp or dxf).
- Are documents missing? The ministry reports this within 5 working days. You then have 2 weeks to supplement them; otherwise the application is rejected.
What does a subdivision application cost?
The ministry calculates the fees (leges) in advance; you pay them at submission. In addition, Major One charges for the surveying work and the subdivision plan.
Subdivision plans are priced individually, from USD 3,000. We will contact you within 3 working days.
Frequently asked questions about subdividing
When do I need a subdivision permit?
If you want to divide a parcel into several parcels, for family or for commercial use, you may need a subdivision permit. In doubt, contact us.
What is a parent map (moederkaart)?
The parent map is the map of the original parcel that you want to divide. According to the checklist, that map must have a Parcel ID.
What is the difference between a small and a large subdivision?
Large subdivisions require additional technical plans and a longer procedure, including a declaration of readiness (bereidverklaring). We help you assess which category your plan falls into.
Who may prepare the subdivision plan?
For small family subdivisions a land surveyor can prepare the design plan. For large subdivisions, according to the manual of the ministry, the application and design must be prepared by a registered engineering firm. Land surveyors certify, among other things, the parcel map, the subdivision map and the spot height map.
How long does the application take?
The manual does not state a total lead time. The ministry reports missing documents within 5 working days; you then have 2 weeks to supplement them. A complete file prevents delay.
What happens if my file is not complete?
If documents are missing, you receive a notice and have 2 weeks to provide them. If that does not happen, the application is rejected.
What does a subdivision plan cost?
Subdivision plans are priced individually. You see the current indicative price on this page. The ministry fees (leges) are charged separately.
Contact and opening hours
- Address: Samuel Kafiludistraat 42, Paramaribo
- Phone: 400-564 / 845-1623 / 875-1514
- E-mail: contact@majoronesurveying.com
- Opening hours: 08:00 to 16:00
Last updated: October 2026